Multnomah County plan check and resubmittal guide
What we could verify about Multnomah County’s permit office from government and permit portal pages, what Oregon law says about plan check there, and how to answer a correction letter. Each fact links to its source.
Multnomah County permit office
- Portland Permitting & Development (PP&D): 503-823-7300 (portland.gov, checked October 31, 2026)
- Address: 1900 SW Fourth Avenue, First floor lobby, Portland, OR 97201 (portland.gov, checked October 31, 2026)
- Resubmittal instructions
Links and facts checked on October 31, 2026.
How to resubmit after Multnomah County plan check corrections
- Make changes and corrections on plan sets.
- Check the box under Acknowledgements.
From Multnomah County’s own page, read October 31, 2026: portland.gov
What to include
- The reviewer issued checksheet.
- The checksheet response form.
- Supplemental or Replacement Calculations (as needed).
- Reference Materials (as needed).
- Upload pages that have changed, only.
- Ensure a “submitted” date stamp is on every page.
- PDF files should not be locked or contain electronic signatures.
From Multnomah County’s own page, read October 31, 2026: portland.gov
Codes its letters cite
Local amendments to the building code
The state building code is uniform statewide: cities and counties may not set different requirements unless the state Building Codes Division authorizes them.
Multnomah County and Oregon
Guides for places in Multnomah County:
Oregon rules every plan check here follows
These come from Oregon law and state agencies, so they apply in Multnomah County as well. Each links to its source.
Residential code
The 2026 Oregon Residential Specialty Code took effect on Oct. 1, 2026. Chapter 1 is already mandatory; Chapters 2 - 44 and the appendices become mandatory on April 1, 2027.
Source: Oregon Building Codes Division, checked October 31, 2026
Commercial (structural) code
Commercial buildings follow the 2025 Oregon Structural Specialty Code. It took effect Oct. 1, 2025, and after a 6-month phase-in became mandatory on April 1, 2026.
Source: Oregon Building Codes Division, checked October 31, 2026
Commercial energy code
Energy rules for commercial buildings come from the 2025 Oregon Energy Efficiency Specialty Code, mandatory since July 1, 2025.
Source: Oregon Building Codes Division, checked October 31, 2026
Electrical code
Electrical work follows the 2026 Oregon Electrical Specialty Code, based on the 2026 National Electrical Code, in effect since Oct. 1, 2026.
Source: Oregon Building Codes Division, checked October 31, 2026
Plumbing code
Plumbing work follows the 2026 Oregon Plumbing Specialty Code, based on the 2024 Uniform Plumbing Code, in effect since Oct. 1, 2026.
Source: Oregon Building Codes Division, checked October 31, 2026
What a good response to checksheet has
General guidance, not Multnomah County’s own rules. Check its page before you resubmit.
- Answer every comment, in the reviewer’s order and numbering, so nothing is missed.
- Say plainly what you changed for each comment, or why no change is needed.
- Name the sheet and detail where each change is, so the reviewer can find it fast.
- Mark changes on the drawings (clouds or deltas are common) and keep sheet numbers the same.
- Send the response letter, the revised drawings and any new calculations together.
Other Oregon city guides
How we help
Send us the whole checksheet. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to Multnomah County yourself.
Cleared to Build is an independent service. We are not Multnomah County and are not affiliated with it.
Upload your correction letterOnly one comment to answer? Try the free one-comment tool.
Questions
What does Multnomah County call its correction letter?
Multnomah County calls it “checksheet”.
How do I resubmit after Multnomah County sends corrections?
Make changes and corrections on plan sets.; then Check the box under Acknowledgements.
How long does Multnomah County take to review a resubmittal?
Review times change with workload. Ask the building department at 503-823-7300.
Does Multnomah County charge for another plan review?
This guide doesn’t list fees. Ask Portland Permitting & Development (PP&D) at 503-823-7300 before you resubmit.
How many rounds of corrections can Multnomah County send?
This guide doesn’t list a limit. Answering every comment fully the first time is the surest way to fewer rounds; ask Portland Permitting & Development (PP&D) at 503-823-7300 if unsure.