How to resubmit
- Review comments are in two places in the Permit Portal, so check both: the Reviews tab and the Attachments tab of the case.
- On the Reviews tab, open the review you need (usually the most current version), then click Details for each department to see its comments.
- On the Attachments tab, open the documents staff uploaded; their Notes column shows the department name and a reference to comments.
- To upload a corrected document, open the plan or permit, go to Attachments, click Add Attachment, check the file in the list and click Submit.
From the city’s instructions: s3.us-west-1.amazonaws.com
Codes its letters cite
Building code named on the city’s pages: 2018 North Carolina State Building Code.
Local amendments to the building code
The North Carolina State Building Code applies statewide and local governments cannot amend it, except local fire-prevention rules that the state Code Council has signed off.
Official links
Links and facts checked on October 31, 2026.
North Carolina rules every plan check here follows
These come from North Carolina law and state agencies, so they apply in Wake County as well. Each links to its source.
Code for homes
The 2018 North Carolina Residential Code has applied since January 1, 2019.
Source: NC Office of State Fire Marshal, checked October 31, 2026
Other building codes
The 2018 North Carolina building, energy, fire, mechanical and plumbing codes have applied since January 1, 2019.
Source: NC Office of State Fire Marshal, checked October 31, 2026
The 2024 code is not in force yet
The 2024 North Carolina State Building Code starts 12 months after the State Fire Marshal certifies that set steps are done, so check the date before you design to it.
Source: NC State Fire Marshal letter on the 2024 code, checked October 31, 2026
What a good response to plan check corrections has
General guidance, not Wake County’s own rules. Check its page before you resubmit.
- Answer every comment, in the reviewer’s order and numbering, so nothing is missed.
- Say plainly what you changed for each comment, or why no change is needed.
- Name the sheet and detail where each change is, so the reviewer can find it fast.
- Mark changes on the drawings (clouds or deltas are common) and keep sheet numbers the same.
- Send the response letter, the revised drawings and any new calculations together.
Other North Carolina city guides
How we help
Send us the whole correction letter. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to Wake County yourself.
Cleared to Build is an independent service. We are not Wake County and are not affiliated with it.
Upload your correction letterOnly one comment to answer? Try the free one-comment tool.
Questions
How do I resubmit after Wake County sends corrections?
Complete the Amendment Permit Form and gather your revised building and site plans. Attach the form and plans to the existing permit in the permit portal.
How do I respond to Wake County’s plan check corrections?
In short: Complete the Amendment Permit Form and gather your revised building and site plans. Attach the form and plans to the existing permit in the permit portal. Answer every comment in a response letter that says what changed and on which sheet.
Is Cleared to Build part of Wake County?
No. Cleared to Build is an independent service, not affiliated with Wake County or any permitting agency. You submit to the city yourself.