How to respond to Mill Valley’s plan check review report
How to resubmit to the City of Mill Valley after plan check corrections, in the words of Mill Valley’s own page. Each fact links to its source.
From Mill Valley’s own page, read October 30, 2026: cityofmillvalley.gov
What the City of Mill Valley calls it
The City of Mill Valley calls its correction letter “plan check review report”.
How to resubmit after Mill Valley plan check corrections
- Please allow one week for second reviews.
From Mill Valley’s own page, read October 30, 2026: cityofmillvalley.gov
What to include
- Any Accompanying Docs (such as Supplemental/Revised Calcs, Geo-Tech Review Letter, Product Info, if applicable
- Only .pdf files are accepted.
- Upload complete submittals only.
From Mill Valley’s own page, read October 30, 2026: cityofmillvalley.gov
Codes its letters cite
Local amendments to the building code
None listed by the California Building Standards Commission as of 2026-10-31. The Commission is still posting 2025 filings, and a place that adopts the state code without changes does not file, so check the city's own adoption ordinance.
Official links
- Resubmittal instructions
- eTRAKiT
- Building department page
- Building Division: 415-388-4033 (cityofmillvalley.gov, checked October 31, 2026)
- Address: 26 Corte Madera Avenue, Mill Valley, CA 94941 (cityofmillvalley.gov, checked October 31, 2026)
Links and facts checked on October 28, 2026.
California rules every plan check here follows
These come from California law and state agencies, so they apply in Mill Valley as well. Each links to its source.
Building code in force
The 2025 edition of Title 24, the California Building Standards Code, has been in effect since January 1, 2026.
Source: California Building Standards Commission, checked October 31, 2026
Energy code
If your permit application was filed on or after January 1, 2026, the project has to meet the 2025 Energy Code.
Source: California Energy Commission, checked October 31, 2026
Energy forms with the application
A building permit application covered by the energy code (Part 6) must include at least one copy of the required energy compliance documents.
Source: California Energy Commission, 2025 Building Energy Efficiency Standards, checked October 31, 2026
Green building code (CALGreen)
The 2025 edition of CALGreen, the state green building code (Part 11), took effect on January 1, 2026.
Source: California Building Standards Commission, checked October 31, 2026
ADU decision deadline
If the city or county has not approved or denied a complete application for an ADU or junior ADU within 60 days, the application is treated as approved (Gov. Code § 66317).
Source: California Department of Housing and Community Development, ADU Handbook, checked October 31, 2026
ADU denials must explain the fix
When a city or county denies an ADU or junior ADU application, it must send written comments within 60 days that list each problem and explain how you can correct it.
Source: California Department of Housing and Community Development, ADU Handbook, checked October 31, 2026
Building permits for approved housing projects
For housing projects that already have planning approval, the city or county has 15 business days to say whether a building permit application is complete, then 30 or 60 days, depending on how many units are proposed, to decide whether it meets the standards.
Source: California Department of Housing and Community Development, Housing Law Fact Sheets, checked October 31, 2026
What a good response to plan check review report has
General guidance, not the City of Mill Valley’s own rules. Check its page before you resubmit.
- Answer every comment, in the reviewer’s order and numbering, so nothing is missed.
- Say plainly what you changed for each comment, or why no change is needed.
- Name the sheet and detail where each change is, so the reviewer can find it fast.
- Mark changes on the drawings (clouds or deltas are common) and keep sheet numbers the same.
- Send the response letter, the revised drawings and any new calculations together.
Other California city guides
How we help
Send us the whole plan check review report. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to the City of Mill Valley yourself.
Cleared to Build is an independent service. We are not the City of Mill Valley and are not affiliated with it.
Upload your correction letterOnly one comment to answer? Try the free one-comment tool.
Questions
What does the City of Mill Valley call its correction letter?
The City of Mill Valley calls it “plan check review report”.
How do I resubmit after the City of Mill Valley sends corrections?
Please allow one week for second reviews.
What should a resubmittal to Mill Valley include?
In general: a response letter answering each comment, the revised drawings with changes marked, and any new calculations or reports the comments ask for. The City of Mill Valley may ask for more, so check with it before you send.
Where do I send my resubmittal to Mill Valley?
The City of Mill Valley’s online permit portal is eTRAKiT, linked on this page. Ask the building department how it wants resubmittals sent if its instructions don’t say.
Does Mill Valley charge for another plan review?
This guide doesn’t list fees. Ask Building Division at 415-388-4033 before you resubmit.
How many rounds of corrections can Mill Valley send?
This guide doesn’t list a limit. Answering every comment fully the first time is the surest way to fewer rounds; ask Building Division at 415-388-4033 if unsure.