How to respond to Corte Madera plan check corrections
How to resubmit to the Town of Corte Madera after plan check corrections, in the words of Corte Madera’s own page. Each fact links to its source.
From Corte Madera’s own page, read October 30, 2026: aca-prod.accela.com
How to resubmit
- Complete the Revisions to Approved Plans Form by clicking here.
- Find the Record/Permit # that you want to revise.
- Select Record Details, and select "Attachments"
- Upload resubmittal and revision documents to the original record.
From Corte Madera’s own page, read October 30, 2026: aca-prod.accela.com
Codes its letters cite
Local amendments to the building code
Filed local amendments with the California Building Standards Commission (ordinance 1048, 1049, 1050).
Official links
- Resubmittal instructions
- Accela Citizen Access
- Building department page
- Building Division: 415-927-5128 (cortemadera.gov, checked October 31, 2026)
- Address: 300 Tamalpais Drive, Corte Madera, CA 94925 (cortemadera.gov, checked October 31, 2026)
Links and facts checked on October 28, 2026.
California rules every plan check here follows
These come from California law and state agencies, so they apply in Corte Madera as well. Each links to its source.
Building code in force
The 2025 edition of Title 24, the California Building Standards Code, has been in effect since January 1, 2026.
Source: California Building Standards Commission, checked October 31, 2026
Energy code
If your permit application was filed on or after January 1, 2026, the project has to meet the 2025 Energy Code.
Source: California Energy Commission, checked October 31, 2026
Energy forms with the application
A building permit application covered by the energy code (Part 6) must include at least one copy of the required energy compliance documents.
Source: California Energy Commission, 2025 Building Energy Efficiency Standards, checked October 31, 2026
Green building code (CALGreen)
The 2025 edition of CALGreen, the state green building code (Part 11), took effect on January 1, 2026.
Source: California Building Standards Commission, checked October 31, 2026
ADU decision deadline
If the city or county has not approved or denied a complete application for an ADU or junior ADU within 60 days, the application is treated as approved (Gov. Code § 66317).
Source: California Department of Housing and Community Development, ADU Handbook, checked October 31, 2026
ADU denials must explain the fix
When a city or county denies an ADU or junior ADU application, it must send written comments within 60 days that list each problem and explain how you can correct it.
Source: California Department of Housing and Community Development, ADU Handbook, checked October 31, 2026
Building permits for approved housing projects
For housing projects that already have planning approval, the city or county has 15 business days to say whether a building permit application is complete, then 30 or 60 days, depending on how many units are proposed, to decide whether it meets the standards.
Source: California Department of Housing and Community Development, Housing Law Fact Sheets, checked October 31, 2026
What a good response to plan check corrections has
General guidance, not the Town of Corte Madera’s own rules. Check its page before you resubmit.
- Answer every comment, in the reviewer’s order and numbering, so nothing is missed.
- Say plainly what you changed for each comment, or why no change is needed.
- Name the sheet and detail where each change is, so the reviewer can find it fast.
- Mark changes on the drawings (clouds or deltas are common) and keep sheet numbers the same.
- Send the response letter, the revised drawings and any new calculations together.
Other California city guides
How we help
Send us the whole correction letter. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to the Town of Corte Madera yourself.
Cleared to Build is an independent service. We are not the Town of Corte Madera and are not affiliated with it.
Upload your correction letterOnly one comment to answer? Try the free one-comment tool.
Questions
How do I resubmit after the Town of Corte Madera sends corrections?
Look up the record or permit number you want to change. Open Record Details and choose the Attachments section. Send your resubmittal and revision files into that same original record.
How do I respond to Corte Madera’s plan check corrections?
In short: Look up the record or permit number you want to change. Open Record Details and choose the Attachments section. Send your resubmittal and revision files into that same original record. Answer every comment in a response letter that says what changed and on which sheet.
What should a resubmittal to Corte Madera include?
In general: a response letter answering each comment, the revised drawings with changes marked, and any new calculations or reports the comments ask for. The Town of Corte Madera may ask for more, so check with it before you send.
How long does Corte Madera take to review a resubmittal?
For housing projects that already have planning approval, the city or county has 15 business days to say whether a building permit application is complete, then 30 or 60 days, depending on how many units are proposed, to decide whether it meets the standards. Ask the Town of Corte Madera for its current review times.
Whom do I ask about Corte Madera’s plan check corrections?
Call Building Division at 415-927-5128. For a question about one comment, ask for the reviewer named on the letter.
Does Corte Madera charge for another plan review?
This guide doesn’t list fees. Ask Building Division at 415-927-5128 before you resubmit.
How many rounds of corrections can Corte Madera send?
This guide doesn’t list a limit. Answering every comment fully the first time is the surest way to fewer rounds; ask Building Division at 415-927-5128 if unsure.
Is Cleared to Build part of the Town of Corte Madera?
No. Cleared to Build is an independent service, not affiliated with the Town of Corte Madera or any permitting agency. You submit to the city yourself.