How to respond to Scottsdale plan check corrections

What the City of Scottsdale calls its correction letter, how to resubmit, and what to include, from the city’s own pages. Each fact links to its source.

How to resubmit

  1. Open the record in Scottsdale SPUR; the markups explain why each document needs to be resubmitted.
  2. To reply to the staff reviewer, click Respond and enter your text.
  3. Select the corrected file to upload and click Submit.

From the city’s instructions: scottsdaleaz.gov

What to include

From Scottsdale’s own page, read October 31, 2026: scottsdaleaz.gov

Codes its letters cite

Building code named on the city’s pages: 2021 International Building Code (IBC) with 2021 City Amendments (effective Jan. 1, 2023).

Source: scottsdaleaz.gov

Local amendments to the building code

Arizona has no statewide building code: each city, town and county adopts its own code edition and amendments by ordinance.

Source: azleg.gov

Official links

Links and facts checked on October 30, 2026.

Arizona rules every plan check here follows

These come from Arizona law and state agencies, so they apply in Scottsdale as well. Each links to its source.

Permits are covered

These state rules on review times apply to city and town permits and approvals, not just business licenses.

Source: Arizona Revised Statutes § 9-831, checked October 31, 2026

Posted review times

Each city or town must post its permit time frames online, showing the completeness check and the technical review as separate periods.

Source: Arizona Revised Statutes § 9-835, checked October 31, 2026

One full set of corrections

During the technical review, the city or town may send you one comprehensive written list of corrections.

Source: Arizona Revised Statutes § 9-835, checked October 31, 2026

A meeting about corrections

If you ask, the city or town must meet or talk with you about its corrections within ten working days and give you enough guidance to make them.

Source: Arizona Revised Statutes § 9-835, checked October 31, 2026

Fee refund for missed deadlines

For residential building or land development permits, if the city or town goes beyond the allowed rounds of corrections or misses its overall time frame, it must refund all review fees without you having to ask.

Source: Arizona Revised Statutes § 9-835, checked October 31, 2026

What a good response to plan check corrections has

General guidance, not the City of Scottsdale’s own rules. Check its page before you resubmit.

Other Arizona city guides

How we help

Send us the whole correction letter. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to the City of Scottsdale yourself.

Cleared to Build is an independent service. We are not the City of Scottsdale and are not affiliated with it.

Upload your correction letter

Only one comment to answer? Try the free one-comment tool.

Questions

How do I resubmit after the City of Scottsdale sends corrections?

Choose the new file you want to upload.

How do I respond to Scottsdale’s plan check corrections?

In short: Choose the new file you want to upload. Answer every comment in a response letter that says what changed and on which sheet.

What should a resubmittal to Scottsdale include?

In general: a response letter answering each comment, the revised drawings with changes marked, and any new calculations or reports the comments ask for. The City of Scottsdale may ask for more, so check with it before you send.

How long does Scottsdale take to review a resubmittal?

Each city or town must post its permit time frames online, showing the completeness check and the technical review as separate periods. Ask the City of Scottsdale for its current review times.

Whom do I ask about Scottsdale’s plan check corrections?

Call Planning and Development Services at 480-312-2500. For a question about one comment, ask for the reviewer named on the letter.

Does Scottsdale charge for another plan review?

This guide doesn’t list fees. Ask Planning and Development Services at 480-312-2500 before you resubmit.

How many rounds of corrections can Scottsdale send?

During the technical review, the city or town may send you one comprehensive written list of corrections.