How to respond to Chandler’s corrections report

What the City of Chandler calls its correction letter, how to resubmit, and what to include, from the city’s own pages. Each fact links to its source.

What the City of Chandler calls it

The City of Chandler calls its correction letter “corrections report”.

Source: chandleraz.gov

How to resubmit after Chandler plan check corrections

  1. For a required resubmittal, use file names like the original marked-up submittal, noting any file names staff changed.
  2. Resubmit corrected plan sets in the same page order; do not reorder, extract or insert pages in the middle of a set.
  3. Put new sheets at the end of the set, and replace removed sheets with a blank page or cross them out.
  4. Revisions or deferred submittals to approved plans go by email to plans.coordination@chandleraz.gov with the original permit or record number, not as a new record.

From the city’s instructions: chandleraz.gov

What to include

From the city’s instructions: chandleraz.gov

Codes its letters cite

Building code named on the city’s pages: 2024 editions of the International Codes.

Source: chandleraz.gov

Local amendments to the building code

Arizona has no statewide building code: each city, town and county adopts its own code edition and amendments by ordinance.

Source: azleg.gov

Official links

Links and facts checked on October 28, 2026.

Arizona rules every plan check here follows

These come from Arizona law and state agencies, so they apply in Chandler as well. Each links to its source.

Permits are covered

These state rules on review times apply to city and town permits and approvals, not just business licenses.

Source: Arizona Revised Statutes § 9-831, checked October 31, 2026

Posted review times

Each city or town must post its permit time frames online, showing the completeness check and the technical review as separate periods.

Source: Arizona Revised Statutes § 9-835, checked October 31, 2026

One full set of corrections

During the technical review, the city or town may send you one comprehensive written list of corrections.

Source: Arizona Revised Statutes § 9-835, checked October 31, 2026

A meeting about corrections

If you ask, the city or town must meet or talk with you about its corrections within ten working days and give you enough guidance to make them.

Source: Arizona Revised Statutes § 9-835, checked October 31, 2026

Fee refund for missed deadlines

For residential building or land development permits, if the city or town goes beyond the allowed rounds of corrections or misses its overall time frame, it must refund all review fees without you having to ask.

Source: Arizona Revised Statutes § 9-835, checked October 31, 2026

What a good response to corrections report has

General guidance, not the City of Chandler’s own rules. Check its page before you resubmit.

Other Arizona city guides

How we help

Send us the whole corrections report. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to the City of Chandler yourself.

Cleared to Build is an independent service. We are not the City of Chandler and are not affiliated with it.

Upload your correction letter

Only one comment to answer? Try the free one-comment tool.

Questions

What does the City of Chandler call its correction letter?

The City of Chandler calls it “corrections report”.

How do I resubmit after the City of Chandler sends corrections?

Keep your original submitted file so you can confirm the sheet order later.

How do I respond to Chandler’s corrections report?

In short: Keep your original submitted file so you can confirm the sheet order later. Answer every comment in a response letter that says what changed and on which sheet.

What should a resubmittal to Chandler include?

In general: a response letter answering each comment, the revised drawings with changes marked, and any new calculations or reports the comments ask for. The City of Chandler may ask for more, so check with it before you send.

Where do I send my resubmittal to Chandler?

The City of Chandler’s online permit portal is Citizen Access Portal, linked on this page. Ask the building department how it wants resubmittals sent if its instructions don’t say.

How long does Chandler take to review a resubmittal?

Each city or town must post its permit time frames online, showing the completeness check and the technical review as separate periods. Ask the City of Chandler for its current review times.

How many rounds of corrections can Chandler send?

During the technical review, the city or town may send you one comprehensive written list of corrections.