How to respond to Phoenix’s Reviewer's Notes

What the City of Phoenix calls its correction letter, how to resubmit, and what to include, from the city’s own pages. Each fact links to its source.

What the City of Phoenix calls it

The City of Phoenix calls its correction letter “Reviewer's Notes”.

Reviewer's Notes: LPRM-2107684

Source: apps-secure.phoenix.gov

How to resubmit after Phoenix plan check corrections

  1. Resubmitted file names must be consistent with the previous submittal and end with the next _V#: a file received with markups as Arch_Plans_V1.pdf is resubmitted as Arch_Plans_V2.pdf.
  2. Upload PDFs only, unlocked and unprotected so reviewers can place markups and stamps: no zip files, no digital signature certifications, layers merged or flattened.
  3. Keep each discipline's plan sheets in one multi-sheet PDF, and supporting documents (calculations, reports, certificates) in one PDF per content type.
  4. Files that don't meet these requirements are rejected at intake until uploaded correctly.

From the city’s instructions: phoenix.gov

What to include

From the city’s instructions: phoenix.gov

Codes its letters cite

Local code abbreviations you will see on the City of Phoenix letters: PBCC.

Source: phoenix.gov

Building code named on the city’s pages: 2024 Phoenix Building Construction Code.

Source: phoenix.gov

Local amendments to the building code

Adopted local amendments.

Source: phoenix.gov

Sections the City of Phoenix changes from the state code (summaries in our words; read the ordinance for the exact text):

The ordinance amends more sections than these.

The amendments: phoenix.gov

Official links

Links and facts checked on October 30, 2026.

Arizona rules every plan check here follows

These come from Arizona law and state agencies, so they apply in Phoenix as well. Each links to its source.

Permits are covered

These state rules on review times apply to city and town permits and approvals, not just business licenses.

Source: Arizona Revised Statutes § 9-831, checked October 31, 2026

Posted review times

Each city or town must post its permit time frames online, showing the completeness check and the technical review as separate periods.

Source: Arizona Revised Statutes § 9-835, checked October 31, 2026

One full set of corrections

During the technical review, the city or town may send you one comprehensive written list of corrections.

Source: Arizona Revised Statutes § 9-835, checked October 31, 2026

A meeting about corrections

If you ask, the city or town must meet or talk with you about its corrections within ten working days and give you enough guidance to make them.

Source: Arizona Revised Statutes § 9-835, checked October 31, 2026

Fee refund for missed deadlines

For residential building or land development permits, if the city or town goes beyond the allowed rounds of corrections or misses its overall time frame, it must refund all review fees without you having to ask.

Source: Arizona Revised Statutes § 9-835, checked October 31, 2026

What a good response to Reviewer's Notes has

General guidance, not the City of Phoenix’s own rules. Check its page before you resubmit.

Other Arizona city guides

How we help

Send us the whole Reviewer's Notes. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to the City of Phoenix yourself.

Cleared to Build is an independent service. We are not the City of Phoenix and are not affiliated with it.

Upload your correction letter

Only one comment to answer? Try the free one-comment tool.

Questions

What does the City of Phoenix call its correction letter?

The City of Phoenix calls it “Reviewer's Notes”.

How do I resubmit after the City of Phoenix sends corrections?

Match the resubmitted file name to the earlier submittal's name.

How do I respond to Phoenix’s Reviewer's Notes?

In short: Match the resubmitted file name to the earlier submittal's name. Answer every comment in a response letter that says what changed and on which sheet.

Where do I send my resubmittal to Phoenix?

The City of Phoenix’s online permit portal is SHAPE PHX Portal, linked on this page. Ask the building department how it wants resubmittals sent if its instructions don’t say.

How long does Phoenix take to review a resubmittal?

Each city or town must post its permit time frames online, showing the completeness check and the technical review as separate periods. Ask the City of Phoenix for its current review times.

Does Phoenix charge for another plan review?

This guide doesn’t list fees. Ask Planning and Development Department at 602-262-7811 before you resubmit.

How many rounds of corrections can Phoenix send?

During the technical review, the city or town may send you one comprehensive written list of corrections.