How to resubmit
- Step 1: Sign into your existing account
- Click the “My Records” to locate records associated with your account
- Use the Record Info drop-down and click “Attachments” to upload additional documents.
- Click the ‘Continue Application’ until you reach the Documents & Attachments tab.
- Click “Add”, then click “Add” on the File Upload page.
- Select the document “Type” from the drop-down, then click “Save”.
From Paradise Valley’s own page, read October 30, 2026: paradisevalleyaz.gov
Codes its letters cite
Building code named on the city’s pages: 2015 International Building Code.
Local amendments to the building code
Arizona has no statewide building code: each city, town and county adopts its own code edition and amendments by ordinance.
Official links
- Resubmittal instructions
- Building department page
- Building department: 480-348-3692 (paradisevalleyaz.gov, checked October 31, 2026)
- Address: 6401 E Lincoln Drive, Paradise Valley, AZ 85253-4399 (paradisevalleyaz.gov, checked October 31, 2026)
Links and facts checked on October 30, 2026.
Arizona rules every plan check here follows
These come from Arizona law and state agencies, so they apply in Paradise Valley as well. Each links to its source.
Permits are covered
These state rules on review times apply to city and town permits and approvals, not just business licenses.
Source: Arizona Revised Statutes § 9-831, checked October 31, 2026
Posted review times
Each city or town must post its permit time frames online, showing the completeness check and the technical review as separate periods.
Source: Arizona Revised Statutes § 9-835, checked October 31, 2026
One full set of corrections
During the technical review, the city or town may send you one comprehensive written list of corrections.
Source: Arizona Revised Statutes § 9-835, checked October 31, 2026
A meeting about corrections
If you ask, the city or town must meet or talk with you about its corrections within ten working days and give you enough guidance to make them.
Source: Arizona Revised Statutes § 9-835, checked October 31, 2026
Fee refund for missed deadlines
For residential building or land development permits, if the city or town goes beyond the allowed rounds of corrections or misses its overall time frame, it must refund all review fees without you having to ask.
Source: Arizona Revised Statutes § 9-835, checked October 31, 2026
What a good response to plan check corrections has
General guidance, not the Town of Paradise Valley’s own rules. Check its page before you resubmit.
- Answer every comment, in the reviewer’s order and numbering, so nothing is missed.
- Say plainly what you changed for each comment, or why no change is needed.
- Name the sheet and detail where each change is, so the reviewer can find it fast.
- Mark changes on the drawings (clouds or deltas are common) and keep sheet numbers the same.
- Send the response letter, the revised drawings and any new calculations together.
Other Arizona city guides
How we help
Send us the whole correction letter. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to the Town of Paradise Valley yourself.
Cleared to Build is an independent service. We are not the Town of Paradise Valley and are not affiliated with it.
Upload your correction letterOnly one comment to answer? Try the free one-comment tool.
Questions
How do I resubmit after the Town of Paradise Valley sends corrections?
If the application is in progress, continue until the Documents & Attachments tab appears.
How do I respond to Paradise Valley’s plan check corrections?
In short: If the application is in progress, continue until the Documents & Attachments tab appears. Answer every comment in a response letter that says what changed and on which sheet.
What should a resubmittal to Paradise Valley include?
In general: a response letter answering each comment, the revised drawings with changes marked, and any new calculations or reports the comments ask for. The Town of Paradise Valley may ask for more, so check with it before you send.
How long does Paradise Valley take to review a resubmittal?
Each city or town must post its permit time frames online, showing the completeness check and the technical review as separate periods. Ask the Town of Paradise Valley for its current review times.
Whom do I ask about Paradise Valley’s plan check corrections?
Call the building department at 480-348-3692. For a question about one comment, ask for the reviewer named on the letter.
Does Paradise Valley charge for another plan review?
This guide doesn’t list fees. Ask the building department at 480-348-3692 before you resubmit.
How many rounds of corrections can Paradise Valley send?
During the technical review, the city or town may send you one comprehensive written list of corrections.
Is Cleared to Build part of the Town of Paradise Valley?
No. Cleared to Build is an independent service, not affiliated with the Town of Paradise Valley or any permitting agency. You submit to the city yourself.