How to respond to Glendale’s marked-up package
What the City of Glendale calls its correction letter, how to resubmit, and what to include, from the city’s own pages. Each fact links to its source.
What the City of Glendale calls it
The City of Glendale calls its correction letter “marked-up package”.
How to resubmit after Glendale plan check corrections
- Corrections are requested by email; the email brings a marked-up package describing the revisions or additions needed to the drawings and documents.
- Make the revisions or additions, then upload a new complete set of revised drawings and documents for the next review cycle.
- Delta and cloud all revisions.
- Plans go in as one complete PDF, not individual pages; other documents (application, calculations, reports) go as separate PDFs named by content.
From the city’s instructions: glendaleaz.gov
What to include
- A new complete set of revised drawings and documents, not only the changed sheets
- Every revision clouded with a delta
- All construction sheets in one PDF; calculations, reports and the application as separate PDFs
- Plan sheets 24x36 to 30x42, drawn to scale, sealed and signed
- TrueType fonts, and no red ink in drawings or documents
From the city’s instructions: glendaleaz.gov
Codes its letters cite
Building code named on the city’s pages: 2024 IBC.
Local amendments to the building code
Arizona has no statewide building code: each city, town and county adopts its own code edition and amendments by ordinance.
Official links
- Resubmittal instructions
- Permit portal
- Building department page
- Building Safety Division: 623-930-2800 (glendaleaz.gov, checked October 31, 2026)
- Address: 5850 West Glendale AV, Glendale, AZ 85301 (glendaleaz.gov, checked October 31, 2026)
Links and facts checked on October 30, 2026.
Arizona rules every plan check here follows
These come from Arizona law and state agencies, so they apply in Glendale as well. Each links to its source.
Permits are covered
These state rules on review times apply to city and town permits and approvals, not just business licenses.
Source: Arizona Revised Statutes § 9-831, checked October 31, 2026
Posted review times
Each city or town must post its permit time frames online, showing the completeness check and the technical review as separate periods.
Source: Arizona Revised Statutes § 9-835, checked October 31, 2026
One full set of corrections
During the technical review, the city or town may send you one comprehensive written list of corrections.
Source: Arizona Revised Statutes § 9-835, checked October 31, 2026
A meeting about corrections
If you ask, the city or town must meet or talk with you about its corrections within ten working days and give you enough guidance to make them.
Source: Arizona Revised Statutes § 9-835, checked October 31, 2026
Fee refund for missed deadlines
For residential building or land development permits, if the city or town goes beyond the allowed rounds of corrections or misses its overall time frame, it must refund all review fees without you having to ask.
Source: Arizona Revised Statutes § 9-835, checked October 31, 2026
What a good response to marked-up package has
General guidance, not the City of Glendale’s own rules. Check its page before you resubmit.
- Answer every comment, in the reviewer’s order and numbering, so nothing is missed.
- Say plainly what you changed for each comment, or why no change is needed.
- Name the sheet and detail where each change is, so the reviewer can find it fast.
- Mark changes on the drawings (clouds or deltas are common) and keep sheet numbers the same.
- Send the response letter, the revised drawings and any new calculations together.
Other Arizona city guides
How we help
Send us the whole marked-up package. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to the City of Glendale yourself.
Cleared to Build is an independent service. We are not the City of Glendale and are not affiliated with it.
Upload your correction letterOnly one comment to answer? Try the free one-comment tool.
Questions
What does the City of Glendale call its correction letter?
The City of Glendale calls it “marked-up package”.
How do I resubmit after the City of Glendale sends corrections?
Watch your email for the marked-up package listing the requested revisions and additions.
How long does Glendale take to review a resubmittal?
Each city or town must post its permit time frames online, showing the completeness check and the technical review as separate periods. Ask the City of Glendale for its current review times.
Does Glendale charge for another plan review?
This guide doesn’t list fees. Ask Building Safety Division at 623-930-2800 before you resubmit.
How many rounds of corrections can Glendale send?
During the technical review, the city or town may send you one comprehensive written list of corrections.