What the City of Seattle calls it
The City of Seattle calls its correction letter “Consolidated Summary Report”. It expects a reply to each comment on the marked-up plans.
How to resubmit after Seattle plan check corrections
- Upload corrected plans only after every review on the permit is complete and the status is Corrections Required.
- Reply to each item in the Consolidated Summary Report Plan Set with the Reply function in Bluebeam or the Comment panel of Adobe Acrobat.
- Upload two sets: the Correction Response Plan Set with your replies, and your clean updated Plan Set.
- Always upload a complete plan set; single sheets that only answer the corrections are not reviewed.
From the city’s instructions: seattle.gov
What to include
- Wait until every review is complete and the status is Corrections Required
- Two uploads: the Correction Response Plan Set (your replies) and the clean Plan Set
- A complete plan set, not only the changed sheets
- Sheets landscape, on the right sheet size
- Changed significantly since you applied? Add the Permit Correction Response Letter form (it doesn't replace the replies)
From the city’s instructions: seattle.gov
Codes its letters cite
Local code abbreviations you will see on the City of Seattle letters: SMC, SBC, SRC.
Building code named on the city’s pages: 2021 Seattle Building Code.
Local amendments to the building code
Any city or county may amend the state building code; amendments that affect houses and apartments need State Building Code Council approval first.
The city's adoption page: seattle.gov
Official links
- Resubmittal instructions
- Seattle Services Portal
- Building department page
- Permit open data
- Seattle Department of Construction & Inspections: (206) 684-8600 (seattle.gov, checked October 31, 2026)
- Address: 700 5th Ave, Suite 2000, Seattle, WA, 98104 (seattle.gov, checked October 31, 2026)
Links and facts checked on October 28, 2026.
Washington rules every plan check here follows
These come from Washington law and state agencies, so they apply in Seattle as well. Each links to its source.
Building code in force
Washington's current building code is based on the 2021 model codes and took effect on March 15, 2024.
Source: Washington State Building Code Council, checked October 31, 2026
Next edition
The next update, based on the 2024 codes, is scheduled to take effect on May 3, 2027.
Source: Washington State Building Code Council, checked October 31, 2026
Local amendments
A city or county may change the state code for its own area, but its changes cannot weaken the code's minimum standards.
Source: Washington State Legislature, RCW 19.27.040, checked October 31, 2026
Rules are locked in when you apply
A complete building permit application is reviewed under the building and zoning rules that were in effect on the date it was filed.
Source: Washington State Legislature, RCW 19.27.095, checked October 31, 2026
What a good response to Consolidated Summary Report has
General guidance, not the City of Seattle’s own rules. Check its page before you resubmit.
- Answer every comment, in the reviewer’s order and numbering, so nothing is missed.
- Say plainly what you changed for each comment, or why no change is needed.
- Name the sheet and detail where each change is, so the reviewer can find it fast.
- Mark changes on the drawings (clouds or deltas are common) and keep sheet numbers the same.
- Send the response letter, the revised drawings and any new calculations together.
Other Washington city guides
How we help
Send us the whole Consolidated Summary Report. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to the City of Seattle yourself.
Cleared to Build is an independent service. We are not the City of Seattle and are not affiliated with it.
Upload your correction letterOnly one comment to answer? Try the free one-comment tool.
Questions
What does the City of Seattle call its correction letter?
The City of Seattle calls it “Consolidated Summary Report”. It expects a reply to each comment on the marked-up plans.
How do I resubmit after the City of Seattle sends corrections?
If the proposal changed significantly, complete the response letter form and upload it.
Whom do I ask about Seattle’s Consolidated Summary Report?
Call Seattle Department of Construction & Inspections at (206) 684-8600. For a question about one comment, ask for the reviewer named on the letter.
Does Seattle charge for another plan review?
This guide doesn’t list fees. Ask Seattle Department of Construction & Inspections at (206) 684-8600 before you resubmit.
How many rounds of corrections can Seattle send?
This guide doesn’t list a limit. Answering every comment fully the first time is the surest way to fewer rounds; ask Seattle Department of Construction & Inspections at (206) 684-8600 if unsure.
Is Cleared to Build part of the City of Seattle?
No. Cleared to Build is an independent service, not affiliated with the City of Seattle or any permitting agency. You submit to the city yourself.