How to respond to King County’s summary of correction comments
How to resubmit to King County after plan check corrections, in the words of King County’s own page. Each fact links to its source.
From King County’s own page, read October 30, 2026: kingcounty.gov
What King County calls it
King County calls its correction letter “summary of correction comments”.
After your project is reviewed, you will receive a summary of correction comments.
Source: content.govdelivery.com
What to include after King County plan check corrections
- ProjectDox only accepts drawings and documents in pdf format.
- Avolve ProjectDox requires drawings to be named as follows: King-County-Record-Number_Sheet#_Plan-Type
- ProjectDox automatically versions all plans/drawings that have the same name.
- All the files may be selected and uploaded in ProjectDox simultaneously.
From King County’s own page, read October 30, 2026: kingcounty.gov
Codes its letters cite
Building code named on the city’s pages: 2021 State Building Codes.
Local amendments to the building code
Any city or county may amend the state building code; amendments that affect houses and apartments need State Building Code Council approval first.
Official links
- Resubmittal instructions
- ProjectDox
- Building department page
- King County Permits: 206-296-6600 (kingcounty.gov, checked October 31, 2026)
- Address: 919 SW Grady Way, Suite 300, Renton, WA 98057 (kingcounty.gov, checked October 31, 2026)
Links and facts checked on October 28, 2026.
Washington rules every plan check here follows
These come from Washington law and state agencies, so they apply in King County as well. Each links to its source.
Building code in force
Washington's current building code is based on the 2021 model codes and took effect on March 15, 2024.
Source: Washington State Building Code Council, checked October 31, 2026
Next edition
The next update, based on the 2024 codes, is scheduled to take effect on May 3, 2027.
Source: Washington State Building Code Council, checked October 31, 2026
Local amendments
A city or county may change the state code for its own area, but its changes cannot weaken the code's minimum standards.
Source: Washington State Legislature, RCW 19.27.040, checked October 31, 2026
Rules are locked in when you apply
A complete building permit application is reviewed under the building and zoning rules that were in effect on the date it was filed.
Source: Washington State Legislature, RCW 19.27.095, checked October 31, 2026
What a good response to summary of correction comments has
General guidance, not King County’s own rules. Check its page before you resubmit.
- Answer every comment, in the reviewer’s order and numbering, so nothing is missed.
- Say plainly what you changed for each comment, or why no change is needed.
- Name the sheet and detail where each change is, so the reviewer can find it fast.
- Mark changes on the drawings (clouds or deltas are common) and keep sheet numbers the same.
- Send the response letter, the revised drawings and any new calculations together.
Other Washington city guides
How we help
Send us the whole summary of correction comments. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to King County yourself.
Cleared to Build is an independent service. We are not King County and are not affiliated with it.
Upload your correction letterOnly one comment to answer? Try the free one-comment tool.
Questions
What does King County call its correction letter?
King County calls it “summary of correction comments”.
How long does King County take to review a resubmittal?
Review times change with workload. Ask the building department at 206-296-6600.
Whom do I ask about King County’s summary of correction comments?
Call King County Permits at 206-296-6600. For a question about one comment, ask for the reviewer named on the letter.
Does King County charge for another plan review?
This guide doesn’t list fees. Ask King County Permits at 206-296-6600 before you resubmit.
How many rounds of corrections can King County send?
This guide doesn’t list a limit. Answering every comment fully the first time is the surest way to fewer rounds; ask King County Permits at 206-296-6600 if unsure.
Is Cleared to Build part of King County?
No. Cleared to Build is an independent service, not affiliated with King County or any permitting agency. You submit to the city yourself.