Building permits and plan check in Hatton
Adams County handles building permits for the Town of Hatton. Here is what we could verify about Adams County’s permit office, what Washington law says about plan check, and how to answer a correction letter. Each fact links to its source.
Who handles building permits in Hatton
Building permits for Hatton are handled by Adams County, so plan check corrections and resubmittals go to Adams County. (co.adams.wa.gov, checked October 31, 2026)
Adams County permit office
- Building and Planning: 509-488-9441 (co.adams.wa.gov, checked October 31, 2026)
- Address: 449 E Cedar Boulevard, Othello, WA 99344 (co.adams.wa.gov, checked October 31, 2026)
- Building department page
Links and facts checked on October 28, 2026.
See the full Adams County plan check guide
Hatton and Adams County
Hatton is in Adams County. See the Adams County guide.
Washington rules every plan check here follows
These come from Washington law and state agencies, so they apply in Hatton as well. Each links to its source.
Building code in force
Washington's current building code is based on the 2021 model codes and took effect on March 15, 2024.
Source: Washington State Building Code Council, checked October 31, 2026
Next edition
The next update, based on the 2024 codes, is scheduled to take effect on May 3, 2027.
Source: Washington State Building Code Council, checked October 31, 2026
Local amendments
A city or county may change the state code for its own area, but its changes cannot weaken the code's minimum standards.
Source: Washington State Legislature, RCW 19.27.040, checked October 31, 2026
Rules are locked in when you apply
A complete building permit application is reviewed under the building and zoning rules that were in effect on the date it was filed.
Source: Washington State Legislature, RCW 19.27.095, checked October 31, 2026
What a good response to plan check corrections has
General guidance, not the Town of Hatton’s own rules. Check its page before you resubmit.
- Answer every comment, in the reviewer’s order and numbering, so nothing is missed.
- Say plainly what you changed for each comment, or why no change is needed.
- Name the sheet and detail where each change is, so the reviewer can find it fast.
- Mark changes on the drawings (clouds or deltas are common) and keep sheet numbers the same.
- Send the response letter, the revised drawings and any new calculations together.
Other Washington city guides
How we help
Send us the whole correction letter. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to the Town of Hatton yourself.
Cleared to Build is an independent service. We are not the Town of Hatton and are not affiliated with it.
Upload your correction letterOnly one comment to answer? Try the free one-comment tool.
Questions
Who handles building permits in Hatton?
Adams County does. Send plan check corrections and resubmittals to Adams County, the way its own pages ask.
Is Cleared to Build part of the Town of Hatton or Adams County?
No. Cleared to Build is an independent service, not affiliated with the Town of Hatton, Adams County or any permitting agency. You submit yourself.