What the City of San Antonio calls it

The City of San Antonio calls its correction letter “Issues report”. It expects its own response form.

Source: sa.gov

How to resubmit after San Antonio plan check corrections

  1. Open the permit in the Digital Plan Room in Accela Citizen Access (BuildSA); the Issues report lists the open and answered issues.
  2. Answer every issue for a review discipline; if any issue needs a revised document, answer all of them before submitting the package.
  3. Upload the revised documents in the Uploads tab; reviewers don't see your responses or revised documents until all issues for that discipline are answered and an action is taken in the Uploads tab.

From the city’s instructions: docsonline.sanantonio.gov

Codes its letters cite

Local amendments to the building code

Each Texas city adopts its own building code edition and amendments by ordinance after a public hearing; many North Texas cities use the NCTCOG regional amendments.

Source: statutes.capitol.texas.gov

The city's adoption page: docsonline.sanantonio.gov

Official links

Links and facts checked on October 30, 2026.

Texas rules every plan check here follows

These come from Texas law and state agencies, so they apply in San Antonio as well. Each links to its source.

Code for homes

For houses, Texas cities start from the International Residential Code as it stood on May 1, 2012.

Source: Texas Local Government Code § 214.212, checked October 31, 2026

Code for commercial buildings

For commercial buildings, Texas cities start from the International Building Code as it stood on May 1, 2012.

Source: Texas Local Government Code § 214.216, checked October 31, 2026

Local amendments

Each city can set its own procedures to add to, change, or remove parts of the residential code, and to run its own enforcement.

Source: Texas Local Government Code § 214.212, checked October 31, 2026

Newer code editions

Cities may also consider later code changes published after May 1, 2012, so ask your building department which edition it enforces.

Source: Texas Local Government Code § 214.212, checked October 31, 2026

What a good response to Issues report has

General guidance, not the City of San Antonio’s own rules. Check its page before you resubmit.

Other Texas city guides

How we help

Send us the whole Issues report. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to the City of San Antonio yourself.

Cleared to Build is an independent service. We are not the City of San Antonio and are not affiliated with it.

Upload your correction letter

Only one comment to answer? Try the free one-comment tool.

Questions

What does the City of San Antonio call its correction letter?

The City of San Antonio calls it “Issues report”. It expects its own response form.

How do I resubmit after the City of San Antonio sends corrections?

Phone your plans examiner to find out which items need correcting. Ask the examiner how to resubmit your building plans.

What should a resubmittal to San Antonio include?

In general: a response letter answering each comment, the revised drawings with changes marked, and any new calculations or reports the comments ask for. The City of San Antonio may ask for more, so check with it before you send.

Where do I send my resubmittal to San Antonio?

The City of San Antonio’s online permit portal is BuildSA (Accela Citizen Access Digital Plan Room), linked on this page. Ask the building department how it wants resubmittals sent if its instructions don’t say.

How long does San Antonio take to review a resubmittal?

Review times change with workload. Ask the building department at 210-207-1111.

Does San Antonio charge for another plan review?

This guide doesn’t list fees. Ask Development Services at 210-207-1111 before you resubmit.

How many rounds of corrections can San Antonio send?

This guide doesn’t list a limit. Answering every comment fully the first time is the surest way to fewer rounds; ask Development Services at 210-207-1111 if unsure.

Is Cleared to Build part of the City of San Antonio?

No. Cleared to Build is an independent service, not affiliated with the City of San Antonio or any permitting agency. You submit to the city yourself.