How to respond to Houston plan check corrections
What the City of Houston calls its correction letter, how to resubmit, and what to include, from the city’s own pages. Each fact links to its source.
How to resubmit
- When corrections are required you get a Respond and Resubmit task; log in to ProjectDox, open the project number and go to the Review tab.
- View the reviewer comments and markups and enter a response for each comment in the Applicant Response column.
- Upload a detailed response sheet to the Applicant Responses folder; resubmittals without it are rejected at pre-screen.
- Upload corrected sheets as Versioned Files with the same file name as the original submittal, and any newly requested documents as New Files.
- Check 'I have responded to all review comments' and 'I have uploaded my revised files, if requested', then Submit.
From the city’s instructions: houstonpermittingcenter.org
Codes its letters cite
Building code named on the city’s pages: 2021 Houston Construction Code.
Source: houstonpermittingcenter.org
Local amendments to the building code
Adopted local amendments.
Source: houstonpermittingcenter.org
Sections the City of Houston changes from the state code (summaries in our words; read the ordinance for the exact text):
- IRC R101.1: Title changed to City of Houston Residential Code; jurisdiction name placeholder completed.
- IRC R102.5: Appendices adopted only if referenced; Appendices A, B, C, H, K, L, M, Q, T, U and V adopted.
- IRC R102.8: Refers flammable and combustible liquid storage to Chapter 57 of the Fire Code.
- IRC R102.9: Part VIII-Electrical (Chapters 34-43) of the 2021 Residential Code is not adopted.
- IRC R102.11: Plumber licensing governed by the Plumbing Code and State law; jurisdiction may adopt non-ICC codes.
- IRC R104.10.1: Section deleted in its entirety.
- IRC R104.12: Stop orders issued in the same manner provided in Section 115 of the Building Code.
- IRC R105.2.1: Amended; see the ordinance
- IRC R105.3: Permit application made on a form furnished by the department of building safety; valuation based on aggregate square footage.
- IRC R105.3.1.1: Section deleted in its entirety and reserved.
- IRC R106.1.4: Section deleted in its entirety.
- IRC R108.2: Permit fees set by the applicable governing authority city fee schedule.
The ordinance amends more sections than these.
The amendments: houstonpermittingcenter.org
Official links
- Resubmittal instructions
- Building department page
- Permit open data
- Houston Permitting Center: 832.394.9000 (houstonpermittingcenter.org, checked October 31, 2026)
- Address: 1002 Washington Avenue Houston, TX 77002 (houstonpermittingcenter.org, checked October 31, 2026)
Links and facts checked on October 30, 2026.
Texas rules every plan check here follows
These come from Texas law and state agencies, so they apply in Houston as well. Each links to its source.
Code for homes
For houses, Texas cities start from the International Residential Code as it stood on May 1, 2012.
Source: Texas Local Government Code § 214.212, checked October 31, 2026
Code for commercial buildings
For commercial buildings, Texas cities start from the International Building Code as it stood on May 1, 2012.
Source: Texas Local Government Code § 214.216, checked October 31, 2026
Local amendments
Each city can set its own procedures to add to, change, or remove parts of the residential code, and to run its own enforcement.
Source: Texas Local Government Code § 214.212, checked October 31, 2026
Newer code editions
Cities may also consider later code changes published after May 1, 2012, so ask your building department which edition it enforces.
Source: Texas Local Government Code § 214.212, checked October 31, 2026
What a good response to plan check corrections has
General guidance, not the City of Houston’s own rules. Check its page before you resubmit.
- Answer every comment, in the reviewer’s order and numbering, so nothing is missed.
- Say plainly what you changed for each comment, or why no change is needed.
- Name the sheet and detail where each change is, so the reviewer can find it fast.
- Mark changes on the drawings (clouds or deltas are common) and keep sheet numbers the same.
- Send the response letter, the revised drawings and any new calculations together.
Other Texas city guides
How we help
Send us the whole correction letter. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to the City of Houston yourself.
Cleared to Build is an independent service. We are not the City of Houston and are not affiliated with it.
Upload your correction letterOnly one comment to answer? Try the free one-comment tool.
Questions
How do I resubmit after the City of Houston sends corrections?
Resubmit plans through ProjectDox to the Office of the City Engineer. Write a detailed response for every changemark from the prior review cycle. Enter each response in the Applicant Response column.
How long does Houston take to review a resubmittal?
Review times change with workload. Ask the building department at 832.394.9000.
Does Houston charge for another plan review?
This guide doesn’t list fees. Ask Houston Permitting Center at 832.394.9000 before you resubmit.
How many rounds of corrections can Houston send?
This guide doesn’t list a limit. Answering every comment fully the first time is the surest way to fewer rounds; ask Houston Permitting Center at 832.394.9000 if unsure.