What the City of Fort Worth calls it
The City of Fort Worth calls its correction letter “comments report”. It expects a written response letter that answers each comment.
How to resubmit after Fort Worth plan check corrections
- Revisions can be submitted only after every department has reviewed and the permit is in Awaiting Client Reply status.
- Download the comments report from the permit record; it lists each department's comments (conditions, or holds) and the plans examiner to contact.
- Resubmit all drawings combined into one PDF through Accela Citizen Access, using the Resubmit link in the Attachments section, not by email to the plans examiners.
- A partial submittal of individual sheets is not accepted; resubmit a complete set in the same format and scale as the original.
- Cloud and delta all revisions, with a response letter from the professional that addresses every hold.
From the city’s instructions: fortworthtexas.gov
What to include
- Resubmittals, if necessary, must be submitted in the same format and scale as the original submission.
From Fort Worth’s own page, read October 31, 2026: fortworthtexas.gov
Codes its letters cite
Building code named on the city’s pages: 2021 International Building, Mechanical, Plumbing, Fuel Gas, Fire, and Existing Building Codes.
Local amendments to the building code
Adopted local amendments.
Sections the City of Fort Worth changes from the state code (summaries in our words; read the ordinance for the exact text):
- IBC 307.4: Adds aircraft paint hangars as a new use under Section 307.4.
- IBC 308.2: Adds orphanage and foster home uses under Group I-1.
- IBC 308.3: Adds orphanage and foster home uses under Group I-2.
- IBC 310.2: Adds Bed and Breakfast Inn as a new Group R use.
- IBC 310.4: Amended; see the ordinance
- IBC 310.5: Adds Community Home as a new Group R use.
- IBC 406.5.2.2: Outside horizontal clear space equals one half the height of the highest required opening.
- IBC 424.5: Deletes this section.
- IBC 509.4.2: Adds two sentences on sprinkler head requirements for reduced incidental use areas and existing single-story tenant spaces.
- IBC 903.4: Amended; see the ordinance
- IBC 905.8.1: Amended; see the ordinance
- IBC 907.2: Replaces last sentence requiring manual pull station at sprinkler riser room exit and FACP.
The ordinance amends more sections than these.
The amendments: fortworthtexas.gov
Official links
- Resubmittal instructions
- Accela Citizen Access (ACA)
- Building department page
- Permit open data
- Development Services: 817-392-2222 (fortworthtexas.gov, checked October 31, 2026)
- Address: 100 Fort Worth Trail, Fort Worth, TX 76102 (fortworthtexas.gov, checked October 31, 2026)
Links and facts checked on October 30, 2026.
Texas rules every plan check here follows
These come from Texas law and state agencies, so they apply in Fort Worth as well. Each links to its source.
Code for homes
For houses, Texas cities start from the International Residential Code as it stood on May 1, 2012.
Source: Texas Local Government Code § 214.212, checked October 31, 2026
Code for commercial buildings
For commercial buildings, Texas cities start from the International Building Code as it stood on May 1, 2012.
Source: Texas Local Government Code § 214.216, checked October 31, 2026
Local amendments
Each city can set its own procedures to add to, change, or remove parts of the residential code, and to run its own enforcement.
Source: Texas Local Government Code § 214.212, checked October 31, 2026
Newer code editions
Cities may also consider later code changes published after May 1, 2012, so ask your building department which edition it enforces.
Source: Texas Local Government Code § 214.212, checked October 31, 2026
What a good response to comments report has
General guidance, not the City of Fort Worth’s own rules. Check its page before you resubmit.
- Answer every comment, in the reviewer’s order and numbering, so nothing is missed.
- Say plainly what you changed for each comment, or why no change is needed.
- Name the sheet and detail where each change is, so the reviewer can find it fast.
- Mark changes on the drawings (clouds or deltas are common) and keep sheet numbers the same.
- Send the response letter, the revised drawings and any new calculations together.
Other Texas city guides
How we help
Send us the whole comments report. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to the City of Fort Worth yourself.
Cleared to Build is an independent service. We are not the City of Fort Worth and are not affiliated with it.
Upload your correction letterOnly one comment to answer? Try the free one-comment tool.
Questions
What does the City of Fort Worth call its correction letter?
The City of Fort Worth calls it “comments report”. It expects a written response letter that answers each comment.
How do I resubmit after the City of Fort Worth sends corrections?
Confirm the permit shows Awaiting Client Reply status before submitting any revisions.
How long does Fort Worth take to review a resubmittal?
Review times change with workload. Ask the building department at 817-392-2222.
Does Fort Worth charge for another plan review?
This guide doesn’t list fees. Ask Development Services at 817-392-2222 before you resubmit.
How many rounds of corrections can Fort Worth send?
This guide doesn’t list a limit. Answering every comment fully the first time is the surest way to fewer rounds; ask Development Services at 817-392-2222 if unsure.