How to respond to Reno’s Hold Comment Report

What the City of Reno calls its correction letter, how to resubmit, and what to include, from the city’s own pages. Each fact links to its source.

What the City of Reno calls it

The City of Reno calls its correction letter “Hold Comment Report”. It expects a written response letter that answers each comment.

Source: reno.gov

How to resubmit after Reno plan check corrections

  1. When revisions are required, open the record in OneNV.US and find the Plan Review Hold Comments report on the Digital Projects tab.
  2. Once all comments are addressed, upload a response letter (document type RESPONSE_LETTER) addressing all hold comments, plus every document type named on the Hold Comment report, through Digital Projects.
  3. Keep the same plan sheet reference number for each resubmitted version of a drawing sheet, then submit the package.

From the city’s instructions: reno.gov

What to include

From the city’s instructions: reno.gov

Codes its letters cite

Local code abbreviations you will see on the City of Reno letters: RMC.

Source: reno.gov

Building code named on the city’s pages: 2024 International Building Code.

Source: reno.gov

Local amendments to the building code

Nevada has no statewide building code for private construction: each city and county adopts its own code and amendments by ordinance, mostly the shared Southern or Northern Nevada amendments.

Source: leg.state.nv.us

Official links

Links and facts checked on October 30, 2026.

Nevada rules every plan check here follows

These come from Nevada law and state agencies, so they apply in Reno as well. Each links to its source.

Local building codes

Your city or county chooses its own building code and the rules for enforcing it, so check which code your local building department uses.

Source: Nevada Revised Statutes § 278.580, checked October 31, 2026

Permit fees

Local governments set their own building permit fees, which must be reasonable.

Source: Nevada Revised Statutes § 278.580, checked October 31, 2026

Statewide energy standards

Cities and counties must build the state's minimum energy-efficiency standards into their building codes and enforce them; they may adopt stricter ones.

Source: Nevada Revised Statutes § 701.220, checked October 31, 2026

Energy code updates

The state energy standards follow the International Energy Conservation Code, and the newest version is to be adopted every third year.

Source: Nevada Revised Statutes § 701.220, checked October 31, 2026

What a good response to Hold Comment Report has

General guidance, not the City of Reno’s own rules. Check its page before you resubmit.

Other Nevada city guides

How we help

Send us the whole Hold Comment Report. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to the City of Reno yourself.

Cleared to Build is an independent service. We are not the City of Reno and are not affiliated with it.

Upload your correction letter

Only one comment to answer? Try the free one-comment tool.

Questions

What does the City of Reno call its correction letter?

The City of Reno calls it “Hold Comment Report”. It expects a written response letter that answers each comment.

How do I resubmit after the City of Reno sends corrections?

When revisions are required, open the record in OneNV.US and find the Plan Review Hold Comments report on the Digital Projects tab.; then Once all comments are addressed, upload a response letter (document type RESPONSE_LETTER) addressing all hold comments, plus every document type named on the Hold Comment report, through Digital Projects.; then Keep the same plan sheet reference number for each resubmitted version of a drawing sheet, then submit the package.

How long does Reno take to review a resubmittal?

Review times change with workload. Ask the building department at 775-334-2063.

Does Reno charge for another plan review?

This guide doesn’t list fees. Ask Building & Safety at 775-334-2063 before you resubmit.

How many rounds of corrections can Reno send?

This guide doesn’t list a limit. Answering every comment fully the first time is the surest way to fewer rounds; ask Building & Safety at 775-334-2063 if unsure.

Is Cleared to Build part of the City of Reno?

No. Cleared to Build is an independent service, not affiliated with the City of Reno or any permitting agency. You submit to the city yourself.