How to respond to Mecklenburg County’s redlined plans

What Mecklenburg County calls its correction letter, how to resubmit, and what to include, from the city’s own pages. Each fact links to its source.

What Mecklenburg County calls it

Mecklenburg County calls its correction letter “redlined plans”.

Source: code.mecknc.gov

How to resubmit after Mecklenburg County plan check corrections

  1. If the plans have code deficiencies when the review cycle closes, the system emails the permit applicant and the project designer that revised plans are required, with a link to upload them.
  2. The same link lets the project designer open the redlined plans that identify the corrections needed.
  3. Upload the revised plans through that link; plans and documents must be PDFs, with the plans compiled into one PDF of 40MB or less.
  4. Projects reviewed three or more cycles in the building discipline incur an hourly review fee of $145.00.
  5. Once the plans are approved the permits are issued, and the approved plans are in the contractor's account under the permit.

From the city’s instructions: code.mecknc.gov

What to include

From the city’s instructions: code.mecknc.gov

Codes its letters cite

Building code named on the city’s pages: 2018 North Carolina State Building Code.

Source: ncosfm.gov

Local amendments to the building code

The North Carolina State Building Code applies statewide and local governments cannot amend it, except local fire-prevention rules that the state Code Council has signed off.

Source: ncleg.gov

Official links

Links and facts checked on October 31, 2026.

North Carolina rules every plan check here follows

These come from North Carolina law and state agencies, so they apply in Mecklenburg County as well. Each links to its source.

Code for homes

The 2018 North Carolina Residential Code has applied since January 1, 2019.

Source: NC Office of State Fire Marshal, checked October 31, 2026

Other building codes

The 2018 North Carolina building, energy, fire, mechanical and plumbing codes have applied since January 1, 2019.

Source: NC Office of State Fire Marshal, checked October 31, 2026

The 2024 code is not in force yet

The 2024 North Carolina State Building Code starts 12 months after the State Fire Marshal certifies that set steps are done, so check the date before you design to it.

Source: NC State Fire Marshal letter on the 2024 code, checked October 31, 2026

What a good response to redlined plans has

General guidance, not Mecklenburg County’s own rules. Check its page before you resubmit.

Other North Carolina city guides

How we help

Send us the whole redlined plans. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to Mecklenburg County yourself.

Cleared to Build is an independent service. We are not Mecklenburg County and are not affiliated with it.

Upload your correction letter

Only one comment to answer? Try the free one-comment tool.

Questions

What does Mecklenburg County call its correction letter?

Mecklenburg County calls it “redlined plans”.

How do I resubmit after Mecklenburg County sends corrections?

Designer can open the redlined plans via the link to see corrections.

What should a resubmittal to Mecklenburg County include?

In general: a response letter answering each comment, the revised drawings with changes marked, and any new calculations or reports the comments ask for. Mecklenburg County may ask for more, so check with it before you send.

Is Cleared to Build part of Mecklenburg County?

No. Cleared to Build is an independent service, not affiliated with Mecklenburg County or any permitting agency. You submit to the city yourself.