How to respond to Gwinnett County’s checklist comments

What Gwinnett County calls its correction letter, how to resubmit, and what to include, from the city’s own pages. Each fact links to its source.

What Gwinnett County calls it

Gwinnett County calls its correction letter “checklist comments”.

Source: gwinnettcounty.com

How to resubmit after Gwinnett County plan check corrections

  1. When review is done the County emails you that your plans are ready, with a link to the permit; if the link fails, log in and search for the permit under Building or Development.
  2. All review, resubmittal and comment actions happen on the permit number emailed to you, not on the original plan submittal application.
  3. Open the returned plan from the permit's document list; the blue tags, normally on the required cover sheet, open the checklist comments.
  4. After revising, use the 'Resubmit' link above the plan's 'Actions' drop-down, add the revised plan with a short description and save; a green banner and a confirmation email confirm the resubmittal.
  5. Name each later submittal CaseNumber_CurrentDate_v# (for example SDP2015-00045_04182015_v2), using the case number assigned when comments were returned.

From the city’s instructions: gwinnettcounty.com

What to include

From the city’s instructions: gwinnettcounty.com

Codes its letters cite

Building code named on the city’s pages: International Building Code, 2024 Edition with 2026 Amendments.

Source: gwinnettcounty.com

Local amendments to the building code

A Georgia city or county may adopt stricter local amendments to the state minimum codes for local conditions after sending them to the Department of Community Affairs for review.

Source: dca.georgia.gov

Official links

Links and facts checked on October 31, 2026.

Georgia rules every plan check here follows

These come from Georgia law and state agencies, so they apply in Gwinnett County as well. Each links to its source.

Code for homes

The current state code for homes is the 2024 International Residential Code with Georgia's 2026 amendments.

Source: Georgia Department of Community Affairs, checked October 31, 2026

Codes apply everywhere

The mandatory codes apply to every building in Georgia, even where the local government doesn't enforce them.

Source: Georgia Department of Community Affairs, checked October 31, 2026

What a good response to checklist comments has

General guidance, not Gwinnett County’s own rules. Check its page before you resubmit.

Other Georgia city guides

How we help

Send us the whole checklist comments. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to Gwinnett County yourself.

Cleared to Build is an independent service. We are not Gwinnett County and are not affiliated with it.

Upload your correction letter

Only one comment to answer? Try the free one-comment tool.

Questions

What does Gwinnett County call its correction letter?

Gwinnett County calls it “checklist comments”.

How do I resubmit after Gwinnett County sends corrections?

When review is done the County emails you that your plans are ready, with a link to the permit; if the link fails, log in and search for the permit under Building or Development.; then All review, resubmittal and comment actions happen on the permit number emailed to you, not on the original plan submittal application.; then Open the returned plan from the permit's document list; the blue tags, normally on the required cover sheet, open the checklist comments.; then After revising, use the 'Resubmit' link above the plan's 'Actions' drop-down, add the revised plan with a short description and save; a green banner and a confirmation email confirm the resubmittal.; then Name each later submittal CaseNumber_CurrentDate_v# (for example SDP2015-00045_04182015_v2), using the case number assigned when comments were returned.

How do I respond to Gwinnett County’s checklist comments?

In general, answer every comment in a response letter that says what changed and on which sheet, then resubmit the revised drawings the way Gwinnett County asks. Check its own instructions first.

What should a resubmittal to Gwinnett County include?

In general: a response letter answering each comment, the revised drawings with changes marked, and any new calculations or reports the comments ask for. Gwinnett County may ask for more, so check with it before you send.

Where do I send my resubmittal to Gwinnett County?

Gwinnett County’s online permit portal is Zoning, Inspections, and Permitting Portal, linked on this page. Ask the building department how it wants resubmittals sent if its instructions don’t say.