How to respond to Pembroke Pines plan check corrections

How to resubmit to the City of Pembroke Pines after plan check corrections, in the words of Pembroke Pines’s own page. Each fact links to its source.

From Pembroke Pines’s own page, read October 30, 2026: ppines.com

How to resubmit

  1. Please bring the following:
  2. Please upload the following:
  3. Plans must be uploaded by trade in separate PDF files :

From Pembroke Pines’s own page, read October 30, 2026: ppines.com

What to include

From Pembroke Pines’s own page, read October 30, 2026: ppines.com

Codes its letters cite

Building code named on the city’s pages: Florida Building Code – 8th Edition (2023).

Source: ppines.com

Local amendments to the building code

None listed by the Florida Building Commission as of 2026-10-31. Local technical amendments lapse when the next edition takes effect (the 9th Edition on December 31, 2026).

Source: floridabuilding.org

Official links

Links and facts checked on October 30, 2026.

Florida rules every plan check here follows

These come from Florida law and state agencies, so they apply in Pembroke Pines as well. Each links to its source.

Building code in force

The Florida Building Code, 8th Edition (2023), has been in effect since December 31, 2023.

Source: Florida Building Commission, checked October 31, 2026

Missing-information notice

Within 5 business days of getting your application, the local government must tell you in writing what, if anything, is still needed for the application to count as complete.

Source: Florida Statutes § 553.792, checked October 31, 2026

Review deadline for homes

For a residential unit under 7,500 square feet reviewed by the local government's own plans reviewer, the permit decision is due within 30 business days of a complete application.

Source: Florida Statutes § 553.792, checked October 31, 2026

Answering plan check comments

When the building department sends a written notice of code problems, you have 10 business days to send corrected plans; if you don't, the application will be denied.

Source: Florida Statutes § 553.792, checked October 31, 2026

Review of your corrections

If you resubmit on time, the department then has 10 business days to approve or deny the permit, unless you agree in writing to give it more time.

Source: Florida Statutes § 553.792, checked October 31, 2026

What a good response to plan check corrections has

General guidance, not the City of Pembroke Pines’s own rules. Check its page before you resubmit.

Other Florida city guides

How we help

Send us the whole correction letter. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to the City of Pembroke Pines yourself.

Cleared to Build is an independent service. We are not the City of Pembroke Pines and are not affiliated with it.

Upload your correction letter

Only one comment to answer? Try the free one-comment tool.

Questions

How do I resubmit after the City of Pembroke Pines sends corrections?

Write a response letter answering every review comment. Digitally sign and seal every revised construction plan.

How long does Pembroke Pines take to review a resubmittal?

If you resubmit on time, the department then has 10 business days to approve or deny the permit, unless you agree in writing to give it more time. Ask the City of Pembroke Pines for its current review times.

Does Pembroke Pines charge for another plan review?

This guide doesn’t list fees. Ask The Building Department at 954-450-1060 before you resubmit.

How many rounds of corrections can Pembroke Pines send?

This guide doesn’t list a limit. Answering every comment fully the first time is the surest way to fewer rounds; ask The Building Department at 954-450-1060 if unsure.