Nassau County plan check and resubmittal guide
What we could verify about Nassau County’s permit office from government and permit portal pages, what Florida law says about plan check there, and how to answer a correction letter. Each fact links to its source.
Nassau County permit office
- Building Department: (904) 530-6250 (nassaucountyfl.com, checked October 31, 2026)
- Address: 96161 Nassau Pl., Yulee, FL 32097 (nassaucountyfl.com, checked October 31, 2026)
- Accela
- Building department page
Links and facts checked on October 30, 2026.
Codes its letters cite
Local amendments to the building code
None listed by the Florida Building Commission as of 2026-10-31. Local technical amendments lapse when the next edition takes effect (the 9th Edition on December 31, 2026).
Nassau County and Florida
Nassau County is in Florida.
Florida rules every plan check here follows
These come from Florida law and state agencies, so they apply in Nassau County as well. Each links to its source.
Building code in force
The Florida Building Code, 8th Edition (2023), has been in effect since December 31, 2023.
Source: Florida Building Commission, checked October 31, 2026
Missing-information notice
Within 5 business days of getting your application, the local government must tell you in writing what, if anything, is still needed for the application to count as complete.
Source: Florida Statutes § 553.792, checked October 31, 2026
Review deadline for homes
For a residential unit under 7,500 square feet reviewed by the local government's own plans reviewer, the permit decision is due within 30 business days of a complete application.
Source: Florida Statutes § 553.792, checked October 31, 2026
Answering plan check comments
When the building department sends a written notice of code problems, you have 10 business days to send corrected plans; if you don't, the application will be denied.
Source: Florida Statutes § 553.792, checked October 31, 2026
Review of your corrections
If you resubmit on time, the department then has 10 business days to approve or deny the permit, unless you agree in writing to give it more time.
Source: Florida Statutes § 553.792, checked October 31, 2026
What a good response to plan check corrections has
General guidance, not Nassau County’s own rules. Check its page before you resubmit.
- Answer every comment, in the reviewer’s order and numbering, so nothing is missed.
- Say plainly what you changed for each comment, or why no change is needed.
- Name the sheet and detail where each change is, so the reviewer can find it fast.
- Mark changes on the drawings (clouds or deltas are common) and keep sheet numbers the same.
- Send the response letter, the revised drawings and any new calculations together.
Other Florida city guides
How we help
Send us the whole correction letter. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to Nassau County yourself.
Cleared to Build is an independent service. We are not Nassau County and are not affiliated with it.
Upload your correction letterOnly one comment to answer? Try the free one-comment tool.
Questions
How do I respond to Nassau County’s plan check corrections?
In general, answer every comment in a response letter that says what changed and on which sheet, then resubmit the revised drawings the way Nassau County asks. Check its own instructions first.
What should a resubmittal to Nassau County include?
In general: a response letter answering each comment, the revised drawings with changes marked, and any new calculations or reports the comments ask for. Nassau County may ask for more, so check with it before you send.
Where do I send my resubmittal to Nassau County?
Nassau County’s online permit portal is Accela, linked on this page. Ask the building department how it wants resubmittals sent if its instructions don’t say.
How long does Nassau County take to review a resubmittal?
If you resubmit on time, the department then has 10 business days to approve or deny the permit, unless you agree in writing to give it more time. Ask Nassau County for its current review times.
Whom do I ask about Nassau County’s plan check corrections?
Call Building Department at (904) 530-6250. For a question about one comment, ask for the reviewer named on the letter.
Does Nassau County charge for another plan review?
This guide doesn’t list fees. Ask Building Department at (904) 530-6250 before you resubmit.
How many rounds of corrections can Nassau County send?
This guide doesn’t list a limit. Answering every comment fully the first time is the surest way to fewer rounds; ask Building Department at (904) 530-6250 if unsure.
Is Cleared to Build part of Nassau County?
No. Cleared to Build is an independent service, not affiliated with Nassau County or any permitting agency. You submit to the city yourself.