The City of Maitland permit office
- Building Division: (407) 539-6150 (itsmymaitland.com, checked October 31, 2026)
- Address: 1776 Independence Lane, Maitland, FL 32751 (itsmymaitland.com, checked October 31, 2026)
- Resubmittal instructions
- Building department page
Links and facts checked on October 30, 2026.
How to resubmit, at a glance
In our words, from Maitland’s own page. The exact steps are on the page linked below.
- Cloud every revised area with callouts matching title block and cover revision matrix numbers.
- Write a page-by-page narrative of every change using the Response to Comments Form.
From Maitland’s own page, read October 31, 2026: itsmymaitland.com
Codes its letters cite
Building code named on the city’s pages: Florida Building Code - Building - 8th Edition (2023).
Local amendments to the building code
None listed by the Florida Building Commission as of 2026-10-31. Local technical amendments lapse when the next edition takes effect (the 9th Edition on December 31, 2026).
Maitland and Orange County
Maitland is in Orange County. See the Orange County guide.
Florida rules every plan check here follows
These come from Florida law and state agencies, so they apply in Maitland as well. Each links to its source.
Building code in force
The Florida Building Code, 8th Edition (2023), has been in effect since December 31, 2023.
Source: Florida Building Commission, checked October 31, 2026
Missing-information notice
Within 5 business days of getting your application, the local government must tell you in writing what, if anything, is still needed for the application to count as complete.
Source: Florida Statutes § 553.792, checked October 31, 2026
Review deadline for homes
For a residential unit under 7,500 square feet reviewed by the local government's own plans reviewer, the permit decision is due within 30 business days of a complete application.
Source: Florida Statutes § 553.792, checked October 31, 2026
Answering plan check comments
When the building department sends a written notice of code problems, you have 10 business days to send corrected plans; if you don't, the application will be denied.
Source: Florida Statutes § 553.792, checked October 31, 2026
Review of your corrections
If you resubmit on time, the department then has 10 business days to approve or deny the permit, unless you agree in writing to give it more time.
Source: Florida Statutes § 553.792, checked October 31, 2026
What a good response to plan check corrections has
General guidance, not the City of Maitland’s own rules. Check its page before you resubmit.
- Answer every comment, in the reviewer’s order and numbering, so nothing is missed.
- Say plainly what you changed for each comment, or why no change is needed.
- Name the sheet and detail where each change is, so the reviewer can find it fast.
- Mark changes on the drawings (clouds or deltas are common) and keep sheet numbers the same.
- Send the response letter, the revised drawings and any new calculations together.
Other Florida city guides
How we help
Send us the whole correction letter. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to the City of Maitland yourself.
Cleared to Build is an independent service. We are not the City of Maitland and are not affiliated with it.
Upload your correction letterOnly one comment to answer? Try the free one-comment tool.
Questions
How long does Maitland take to review a resubmittal?
If you resubmit on time, the department then has 10 business days to approve or deny the permit, unless you agree in writing to give it more time. Ask the City of Maitland for its current review times.
Does Maitland charge for another plan review?
This guide doesn’t list fees. Ask Building Division at (407) 539-6150 before you resubmit.
How many rounds of corrections can Maitland send?
This guide doesn’t list a limit. Answering every comment fully the first time is the surest way to fewer rounds; ask Building Division at (407) 539-6150 if unsure.
Is Cleared to Build part of the City of Maitland?
No. Cleared to Build is an independent service, not affiliated with the City of Maitland or any permitting agency. You submit to the city yourself.