Fort Myers plan check and resubmittal guide
What we could verify about the City of Fort Myers’s permit office from government and permit portal pages, what Florida law says about plan check there, and how to answer a correction letter. Each fact links to its source.
The City of Fort Myers permit office
- Building, Permitting & Inspections Division (fortmyers.gov, checked October 31, 2026): 239-321-7925 (fortmyers.gov, checked October 31, 2026)
- Address: 1825 Hendry St., Fort Myers, FL 33901 (fortmyers.gov, checked October 31, 2026)
- Resubmittal instructions
- Building department page
Links and facts checked on October 30, 2026.
How to resubmit after Fort Myers plan check corrections, at a glance
In our words, from Fort Myers’s own page. The exact steps are on the page linked below.
- Check the email on your application for the list of required corrections.
From Fort Myers’s own page, read October 31, 2026: fortmyers.gov
Codes its letters cite
Local amendments to the building code
None listed by the Florida Building Commission as of 2026-10-31. Local technical amendments lapse when the next edition takes effect (the 9th Edition on December 31, 2026).
Fort Myers and Lee County
Fort Myers is in Lee County.
Florida rules every plan check here follows
These come from Florida law and state agencies, so they apply in Fort Myers as well. Each links to its source.
Building code in force
The Florida Building Code, 8th Edition (2023), has been in effect since December 31, 2023.
Source: Florida Building Commission, checked October 31, 2026
Missing-information notice
Within 5 business days of getting your application, the local government must tell you in writing what, if anything, is still needed for the application to count as complete.
Source: Florida Statutes § 553.792, checked October 31, 2026
Review deadline for homes
For a residential unit under 7,500 square feet reviewed by the local government's own plans reviewer, the permit decision is due within 30 business days of a complete application.
Source: Florida Statutes § 553.792, checked October 31, 2026
Answering plan check comments
When the building department sends a written notice of code problems, you have 10 business days to send corrected plans; if you don't, the application will be denied.
Source: Florida Statutes § 553.792, checked October 31, 2026
Review of your corrections
If you resubmit on time, the department then has 10 business days to approve or deny the permit, unless you agree in writing to give it more time.
Source: Florida Statutes § 553.792, checked October 31, 2026
What a good response to plan review comment letter has
General guidance, not the City of Fort Myers’s own rules. Check its page before you resubmit.
- Answer every comment, in the reviewer’s order and numbering, so nothing is missed.
- Say plainly what you changed for each comment, or why no change is needed.
- Name the sheet and detail where each change is, so the reviewer can find it fast.
- Mark changes on the drawings (clouds or deltas are common) and keep sheet numbers the same.
- Send the response letter, the revised drawings and any new calculations together.
Other Florida city guides
How we help
Send us the whole plan review comment letter. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to the City of Fort Myers yourself.
Cleared to Build is an independent service. We are not the City of Fort Myers and are not affiliated with it.
Upload your correction letterOnly one comment to answer? Try the free one-comment tool.
Questions
What does the City of Fort Myers call its correction letter?
The City of Fort Myers calls it “plan review comment letter”.
How long does Fort Myers take to review a resubmittal?
If you resubmit on time, the department then has 10 business days to approve or deny the permit, unless you agree in writing to give it more time. Ask the City of Fort Myers for its current review times.
Does Fort Myers charge for another plan review?
This guide doesn’t list fees. Ask Building, Permitting & Inspections Division at 239-321-7925 before you resubmit.
How many rounds of corrections can Fort Myers send?
This guide doesn’t list a limit. Answering every comment fully the first time is the surest way to fewer rounds; ask Building, Permitting & Inspections Division at 239-321-7925 if unsure.
Is Cleared to Build part of the City of Fort Myers?
No. Cleared to Build is an independent service, not affiliated with the City of Fort Myers or any permitting agency. You submit to the city yourself.