How to respond to Clermont plan check corrections
How to resubmit to the City of Clermont after plan check corrections, in the words of Clermont’s own page. Each fact links to its source.
From Clermont’s own page, read October 30, 2026: clermontfl.gov
How to resubmit, at a glance
In our words, from Clermont’s own page. The exact steps are on the page linked below.
- Pay any additional fire fees, which may apply to the resubmittal.
From Clermont’s own page, read October 31, 2026: clermontfl.gov
What to include
- (3) complete sets of paper plans or (1) set of electronic plans
- Revisions/corrections/additions circled or clouded on each sheet
- Select one resubmittal option (resubmittal to correct noted deficiencies)
- Individual sheets inserted into two sets of paper plans previously submitted, along with the comment/response letter (paper option)
- (1) set of affected drawings for file copy (paper option)
From Clermont’s own page, read October 30, 2026: clermontfl.gov
Codes its letters cite
Local amendments to the building code
None listed by the Florida Building Commission as of 2026-10-31. Local technical amendments lapse when the next edition takes effect (the 9th Edition on December 31, 2026).
Official links
- Resubmittal instructions
- Permit portal
- Building department page
- Building Services: 352-241-7315 (clermontfl.gov, checked October 31, 2026)
- Address: 685 W. Montrose St., Clermont, FL 34711 (clermontfl.gov, checked October 31, 2026)
Links and facts checked on October 30, 2026.
Florida rules every plan check here follows
These come from Florida law and state agencies, so they apply in Clermont as well. Each links to its source.
Building code in force
The Florida Building Code, 8th Edition (2023), has been in effect since December 31, 2023.
Source: Florida Building Commission, checked October 31, 2026
Missing-information notice
Within 5 business days of getting your application, the local government must tell you in writing what, if anything, is still needed for the application to count as complete.
Source: Florida Statutes § 553.792, checked October 31, 2026
Review deadline for homes
For a residential unit under 7,500 square feet reviewed by the local government's own plans reviewer, the permit decision is due within 30 business days of a complete application.
Source: Florida Statutes § 553.792, checked October 31, 2026
Answering plan check comments
When the building department sends a written notice of code problems, you have 10 business days to send corrected plans; if you don't, the application will be denied.
Source: Florida Statutes § 553.792, checked October 31, 2026
Review of your corrections
If you resubmit on time, the department then has 10 business days to approve or deny the permit, unless you agree in writing to give it more time.
Source: Florida Statutes § 553.792, checked October 31, 2026
What a good response to plan check corrections has
General guidance, not the City of Clermont’s own rules. Check its page before you resubmit.
- Answer every comment, in the reviewer’s order and numbering, so nothing is missed.
- Say plainly what you changed for each comment, or why no change is needed.
- Name the sheet and detail where each change is, so the reviewer can find it fast.
- Mark changes on the drawings (clouds or deltas are common) and keep sheet numbers the same.
- Send the response letter, the revised drawings and any new calculations together.
Other Florida city guides
How we help
Send us the whole correction letter. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to the City of Clermont yourself.
Cleared to Build is an independent service. We are not the City of Clermont and are not affiliated with it.
Upload your correction letterOnly one comment to answer? Try the free one-comment tool.
Questions
Where do I send my resubmittal to Clermont?
The City of Clermont’s online permit portal is eTRAKiT portal, linked on this page. Ask the building department how it wants resubmittals sent if its instructions don’t say.
How long does Clermont take to review a resubmittal?
If you resubmit on time, the department then has 10 business days to approve or deny the permit, unless you agree in writing to give it more time. Ask the City of Clermont for its current review times.
Does Clermont charge for another plan review?
This guide doesn’t list fees. Ask Building Services at 352-241-7315 before you resubmit.
How many rounds of corrections can Clermont send?
This guide doesn’t list a limit. Answering every comment fully the first time is the surest way to fewer rounds; ask Building Services at 352-241-7315 if unsure.