How to respond to San Mateo County plan check corrections

How to resubmit to San Mateo County after plan check corrections, in the words of San Mateo County’s own page. Each fact links to its source.

From San Mateo County’s own page, read October 31, 2026: smcgov.org

How to resubmit, at a glance

In our words, from San Mateo County’s own page. The exact steps are on the page linked below.

  1. Assemble 5 sets of revised plans plus the requested information.
  2. Deliver the package at the Building Counter, not to individual review agencies.
  3. Allow a 30-day window for the County to review your resubmittal.

From San Mateo County’s own page, read October 31, 2026: smcgov.org

What to include

From San Mateo County’s own page, read October 31, 2026: smcgov.org

Codes its letters cite

Local amendments to the building code

Filed local amendments with the California Building Standards Commission (ordinance 4916).

Source: dgs.ca.gov

Sections San Mateo County changes from the state code (summaries in our words; read the ordinance for the exact text):

The ordinance amends more sections than these.

The amendments: smcgov.org

Official links

Links and facts checked on October 31, 2026.

California rules every plan check here follows

These come from California law and state agencies, so they apply in San Mateo County as well. Each links to its source.

Building code in force

The 2025 edition of Title 24, the California Building Standards Code, has been in effect since January 1, 2026.

Source: California Building Standards Commission, checked October 31, 2026

Energy code

If your permit application was filed on or after January 1, 2026, the project has to meet the 2025 Energy Code.

Source: California Energy Commission, checked October 31, 2026

Energy forms with the application

A building permit application covered by the energy code (Part 6) must include at least one copy of the required energy compliance documents.

Source: California Energy Commission, 2025 Building Energy Efficiency Standards, checked October 31, 2026

Green building code (CALGreen)

The 2025 edition of CALGreen, the state green building code (Part 11), took effect on January 1, 2026.

Source: California Building Standards Commission, checked October 31, 2026

ADU decision deadline

If the city or county has not approved or denied a complete application for an ADU or junior ADU within 60 days, the application is treated as approved (Gov. Code § 66317).

Source: California Department of Housing and Community Development, ADU Handbook, checked October 31, 2026

ADU denials must explain the fix

When a city or county denies an ADU or junior ADU application, it must send written comments within 60 days that list each problem and explain how you can correct it.

Source: California Department of Housing and Community Development, ADU Handbook, checked October 31, 2026

Building permits for approved housing projects

For housing projects that already have planning approval, the city or county has 15 business days to say whether a building permit application is complete, then 30 or 60 days, depending on how many units are proposed, to decide whether it meets the standards.

Source: California Department of Housing and Community Development, Housing Law Fact Sheets, checked October 31, 2026

What a good response to plan check corrections has

General guidance, not San Mateo County’s own rules. Check its page before you resubmit.

Other California city guides

How we help

Send us the whole correction letter. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to San Mateo County yourself.

Cleared to Build is an independent service. We are not San Mateo County and are not affiliated with it.

Upload your correction letter

Only one comment to answer? Try the free one-comment tool.

Questions

Whom do I ask about San Mateo County’s plan check corrections?

Call Planning and Building Department at (650) 599-7310. For a question about one comment, ask for the reviewer named on the letter.

Does San Mateo County charge for another plan review?

This guide doesn’t list fees. Ask Planning and Building Department at (650) 599-7310 before you resubmit.

How many rounds of corrections can San Mateo County send?

This guide doesn’t list a limit. Answering every comment fully the first time is the surest way to fewer rounds; ask Planning and Building Department at (650) 599-7310 if unsure.

Is Cleared to Build part of San Mateo County?

No. Cleared to Build is an independent service, not affiliated with San Mateo County or any permitting agency. You submit to the city yourself.