How to respond to San Diego’s Cycle Issues report

What the City of San Diego calls its correction letter, how to resubmit, and what to include, from the city’s own pages. Each fact links to its source.

What the City of San Diego calls it

The City of San Diego calls its correction letter “Cycle Issues report”. It expects a written response letter that answers each comment.

Source: sandiego.gov

How to resubmit after San Diego plan check corrections

  1. Respond to every discipline's comments at the same time; you can't resubmit corrections to one discipline separately.
  2. Consolidate the responses into a single file and upload it as the requested file type.
  3. The recheck starts after every document on the Required Submittal report is uploaded.

From the city’s instructions: sandiego.gov

What to include

From the city’s instructions: sandiego.gov

Codes its letters cite

Local code abbreviations you will see on the City of San Diego letters: SDMC.

Building code named on the city’s pages: 2025 California Building Standards Code.

Source: sandiego.gov

Local amendments to the building code

Filed local amendments with the California Building Standards Commission (ordinance 22042, 22043).

Source: dgs.ca.gov

Sections the City of San Diego changes from the state code (summaries in our words; read the ordinance for the exact text):

The ordinance amends more sections than these.

The amendments: sandiego.gov

Official links

Links and facts checked on October 28, 2026.

California rules every plan check here follows

These come from California law and state agencies, so they apply in San Diego as well. Each links to its source.

Building code in force

The 2025 edition of Title 24, the California Building Standards Code, has been in effect since January 1, 2026.

Source: California Building Standards Commission, checked October 31, 2026

Energy code

If your permit application was filed on or after January 1, 2026, the project has to meet the 2025 Energy Code.

Source: California Energy Commission, checked October 31, 2026

Energy forms with the application

A building permit application covered by the energy code (Part 6) must include at least one copy of the required energy compliance documents.

Source: California Energy Commission, 2025 Building Energy Efficiency Standards, checked October 31, 2026

Green building code (CALGreen)

The 2025 edition of CALGreen, the state green building code (Part 11), took effect on January 1, 2026.

Source: California Building Standards Commission, checked October 31, 2026

ADU decision deadline

If the city or county has not approved or denied a complete application for an ADU or junior ADU within 60 days, the application is treated as approved (Gov. Code § 66317).

Source: California Department of Housing and Community Development, ADU Handbook, checked October 31, 2026

ADU denials must explain the fix

When a city or county denies an ADU or junior ADU application, it must send written comments within 60 days that list each problem and explain how you can correct it.

Source: California Department of Housing and Community Development, ADU Handbook, checked October 31, 2026

Building permits for approved housing projects

For housing projects that already have planning approval, the city or county has 15 business days to say whether a building permit application is complete, then 30 or 60 days, depending on how many units are proposed, to decide whether it meets the standards.

Source: California Department of Housing and Community Development, Housing Law Fact Sheets, checked October 31, 2026

What a good response to Cycle Issues report has

General guidance, not the City of San Diego’s own rules. Check its page before you resubmit.

Other California city guides

How we help

Send us the whole Cycle Issues report. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to the City of San Diego yourself.

Cleared to Build is an independent service. We are not the City of San Diego and are not affiliated with it.

Upload your correction letter

Only one comment to answer? Try the free one-comment tool.

Questions

What does the City of San Diego call its correction letter?

The City of San Diego calls it “Cycle Issues report”. It expects a written response letter that answers each comment.

How do I resubmit after the City of San Diego sends corrections?

Wait until every review discipline has finished its cycle before uploading anything.

How long does San Diego take to review a resubmittal?

For housing projects that already have planning approval, the city or county has 15 business days to say whether a building permit application is complete, then 30 or 60 days, depending on how many units are proposed, to decide whether it meets the standards. Ask the City of San Diego for its current review times.

Does San Diego charge for another plan review?

This guide doesn’t list fees. Ask the building department at 619-446-5000 before you resubmit.

How many rounds of corrections can San Diego send?

This guide doesn’t list a limit. Answering every comment fully the first time is the surest way to fewer rounds; ask the building department at 619-446-5000 if unsure.