How to respond to Rialto’s Redlines
How to resubmit to the City of Rialto after plan check corrections, in the words of Rialto’s own page. Each fact links to its source.
What the City of Rialto calls it
The City of Rialto calls its correction letter “Redlines”.
How to resubmit after Rialto plan check corrections, at a glance
In our words, from Rialto’s own page. The exact steps are on the page linked below.
- Confirm the permit shows that corrections are required and plans must be resubmitted.
- Upload the revised documents to the permit application in the portal.
From Rialto’s own page, read October 31, 2026: rialtoca.gov
Codes its letters cite
Building code named on the city’s pages: 2025 California Building Standards.
Local amendments to the building code
Filed local amendments with the California Building Standards Commission (ordinance 1702).
Official links
- Resubmittal instructions
- Building department page
- Building & Safety Division: 909-820-2505 (rialtoca.gov, checked October 31, 2026)
- Address: 150 S Palm Avenue, Rialto, CA 92376 (rialtoca.gov, checked October 31, 2026)
Links and facts checked on October 28, 2026.
California rules every plan check here follows
These come from California law and state agencies, so they apply in Rialto as well. Each links to its source.
Building code in force
The 2025 edition of Title 24, the California Building Standards Code, has been in effect since January 1, 2026.
Source: California Building Standards Commission, checked October 31, 2026
Energy code
If your permit application was filed on or after January 1, 2026, the project has to meet the 2025 Energy Code.
Source: California Energy Commission, checked October 31, 2026
Energy forms with the application
A building permit application covered by the energy code (Part 6) must include at least one copy of the required energy compliance documents.
Source: California Energy Commission, 2025 Building Energy Efficiency Standards, checked October 31, 2026
Green building code (CALGreen)
The 2025 edition of CALGreen, the state green building code (Part 11), took effect on January 1, 2026.
Source: California Building Standards Commission, checked October 31, 2026
ADU decision deadline
If the city or county has not approved or denied a complete application for an ADU or junior ADU within 60 days, the application is treated as approved (Gov. Code § 66317).
Source: California Department of Housing and Community Development, ADU Handbook, checked October 31, 2026
ADU denials must explain the fix
When a city or county denies an ADU or junior ADU application, it must send written comments within 60 days that list each problem and explain how you can correct it.
Source: California Department of Housing and Community Development, ADU Handbook, checked October 31, 2026
Building permits for approved housing projects
For housing projects that already have planning approval, the city or county has 15 business days to say whether a building permit application is complete, then 30 or 60 days, depending on how many units are proposed, to decide whether it meets the standards.
Source: California Department of Housing and Community Development, Housing Law Fact Sheets, checked October 31, 2026
What a good response to Redlines has
General guidance, not the City of Rialto’s own rules. Check its page before you resubmit.
- Answer every comment, in the reviewer’s order and numbering, so nothing is missed.
- Say plainly what you changed for each comment, or why no change is needed.
- Name the sheet and detail where each change is, so the reviewer can find it fast.
- Mark changes on the drawings (clouds or deltas are common) and keep sheet numbers the same.
- Send the response letter, the revised drawings and any new calculations together.
Other California city guides
How we help
Send us the whole Redlines. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to the City of Rialto yourself.
Cleared to Build is an independent service. We are not the City of Rialto and are not affiliated with it.
Upload your correction letterOnly one comment to answer? Try the free one-comment tool.
Questions
What does the City of Rialto call its correction letter?
The City of Rialto calls it “Redlines”.
How do I respond to Rialto’s Redlines?
In short: Confirm the permit shows that corrections are required and plans must be resubmitted. Upload the revised documents to the permit application in the portal. Answer every comment in a response letter that says what changed and on which sheet.
What should a resubmittal to Rialto include?
In general: a response letter answering each comment, the revised drawings with changes marked, and any new calculations or reports the comments ask for. The City of Rialto may ask for more, so check with it before you send.
Where do I send my resubmittal to Rialto?
The City of Rialto’s online permit portal is Online Permitting Center, linked on this page. Ask the building department how it wants resubmittals sent if its instructions don’t say.
How long does Rialto take to review a resubmittal?
For housing projects that already have planning approval, the city or county has 15 business days to say whether a building permit application is complete, then 30 or 60 days, depending on how many units are proposed, to decide whether it meets the standards. Ask the City of Rialto for its current review times.
Does Rialto charge for another plan review?
This guide doesn’t list fees. Ask Building & Safety Division at 909-820-2505 before you resubmit.
How many rounds of corrections can Rialto send?
This guide doesn’t list a limit. Answering every comment fully the first time is the surest way to fewer rounds; ask Building & Safety Division at 909-820-2505 if unsure.