How to respond to Casa Grande plan check corrections

How to resubmit to the City of Casa Grande after plan check corrections, in the words of Casa Grande’s own page. Each fact links to its source.

From Casa Grande’s own page, read October 30, 2026: casagrandeaz.gov

How to resubmit, at a glance

In our words, from Casa Grande’s own page. The exact steps are on the page linked below.

  1. Revise the plans so they are coordinated with each other.

From Casa Grande’s own page, read October 31, 2026: casagrandeaz.gov

What to include

From Casa Grande’s own page, read October 30, 2026: casagrandeaz.gov

Codes its letters cite

Local amendments to the building code

Arizona has no statewide building code: each city, town and county adopts its own code edition and amendments by ordinance.

Source: azleg.gov

Official links

Links and facts checked on October 30, 2026.

Arizona rules every plan check here follows

These come from Arizona law and state agencies, so they apply in Casa Grande as well. Each links to its source.

Permits are covered

These state rules on review times apply to city and town permits and approvals, not just business licenses.

Source: Arizona Revised Statutes § 9-831, checked October 31, 2026

Posted review times

Each city or town must post its permit time frames online, showing the completeness check and the technical review as separate periods.

Source: Arizona Revised Statutes § 9-835, checked October 31, 2026

One full set of corrections

During the technical review, the city or town may send you one comprehensive written list of corrections.

Source: Arizona Revised Statutes § 9-835, checked October 31, 2026

A meeting about corrections

If you ask, the city or town must meet or talk with you about its corrections within ten working days and give you enough guidance to make them.

Source: Arizona Revised Statutes § 9-835, checked October 31, 2026

Fee refund for missed deadlines

For residential building or land development permits, if the city or town goes beyond the allowed rounds of corrections or misses its overall time frame, it must refund all review fees without you having to ask.

Source: Arizona Revised Statutes § 9-835, checked October 31, 2026

What a good response to plan check corrections has

General guidance, not the City of Casa Grande’s own rules. Check its page before you resubmit.

Other Arizona city guides

How we help

Send us the whole correction letter. We draft a response to every comment and list the drawing changes sheet by sheet. Your first letter is free. You review each response, then you sign and submit to the City of Casa Grande yourself.

Cleared to Build is an independent service. We are not the City of Casa Grande and are not affiliated with it.

Upload your correction letter

Only one comment to answer? Try the free one-comment tool.

Questions

Where do I send my resubmittal to Casa Grande?

The City of Casa Grande’s online permit portal is WebPermits, linked on this page. Ask the building department how it wants resubmittals sent if its instructions don’t say.

How long does Casa Grande take to review a resubmittal?

Each city or town must post its permit time frames online, showing the completeness check and the technical review as separate periods. Ask the City of Casa Grande for its current review times.

Does Casa Grande charge for another plan review?

This guide doesn’t list fees. Ask Building Division at 520-421-8630 before you resubmit.

How many rounds of corrections can Casa Grande send?

During the technical review, the city or town may send you one comprehensive written list of corrections.